Power and Renewables

Interconnection Queue Review: Arizona Public Service

byEvan Powell

Arizona Public Service (APS) is the largest energy provider in Arizona, serving about 1.4 million customers across the state. Its territory has emerged as a prime location for renewable energy and battery storage development, largely due to Arizona’s abundant solar resources.

As part of Enverus Project Tracking Analytics, we review project development processes within each utility and interconnection queue across the U.S. to provide a comprehensive project overview.

By delving into trends within the APS interconnection queue, we can gain insight into how APS has nurtured this development, and what the future of the region’s energy landscape will look like.

APS’s place in the nationwide energy landscape

Figure 1- Enverus P&R Project Tracking: Most planned capacity by utility queue

The APS territory is one of the nation’s leaders for power generation development, particularly in renewables and storage. Adding to the rush, the Phoenix area has become a hotbed of data center development as well. Of the 20 major utilities across the nation that we currently track (not including ISOs), APS has the third-most total planned capacity in the queue, trailing only the Bonneville Power Authority and Pacificorp. It also has the third-most planned capacity specifically in each individual category of wind, solar and storage project types as well, reflecting its emphasis on expanding sustainable generation capabilities to support growth.

Figure 2- Enverus P&R Project Tracking: Most total planned capacity by county

On a county level, APS’s prominence is clear. Four of the top 10 counties in the U.S. for total planned capacity are in APS’s territory, including Maricopa County, which leads overall. Additionally, four APS counties are in the top 10 for planned solar capacity and three for storage.

Figure 3- Enverus P&R Project Tracking: Most total planned capacity by state

On a state level, Arizona has the third most total planned capacity in the nation, behind only Texas and California. It has the third most planned storage capacity and the second most planned solar capacity.

Taking the lead in the energy transition

Figure 4- Enverus P&R Project Tracking: Total capacity added to APS queue, by project
type and first queue date

From 2016-2021, there was a rapid and consistent year-over-year uptick in power generation capacity added to the APS Interconnection Queue, comprising almost exclusively renewables and storage projects. Queue activity has cooled slightly since that peak in 2021 but is still consistently far higher than it was before. And as discussed in the previous section, far higher than most of the rest of the country.

Figure 5- Enverus P&R Project Tracking: Projected capacity changes by fuel type over next 15 years, via the most recent IRP goals from APS

Figure 6- Enverus P&R Project Tracking: Operating Capacity in APS by First Power Date

That trend is in line with the most recent APS Integrated Resource Plan, which indicates a commitment to shifting the energy mix away from fossil fuels like coal and towards renewables and storage over the next 15 years. And they are already beginning to deliver on that promise. In 2024 alone the Babbitt Ranch Wind and Chevelon Butte 1 & 2 Wind projects were all brought online, totaling 615 MW of capacity. This followed a productive year for storage projects in 2023, when 251 MW of storage capacity (spread across nine projects) were brought online. The specific project types are different than the IRP projected; it called for more solar thus far and less wind. However, the total renewables plus storage projection for the years 2023 and 2024 was 795 MW, which has been outpaced thus far by the 866 MW built.

Figure 6- Enverus P&R Project Tracking: Operating capacity in APS by first power date

One other interesting feature of the IRP is its approach towards natural gas. In sum, the utility plans to add 409 MW of natural gas over the next 15 years. However, it plans to arrive at that number through a combination of both building but also decommissioning thousands of MWs of natural gas plants, beginning around the year 2030. It appears that they want to more or less maintain their current levels of natural gas usage, but are in a position where they need to invest heavily in the resource in order to do so. That investment indicates that APS has no plans to completely abandon traditional energy sources like gas, even if it isn’t as prominent in their plans as renewables are.

Looking to the future

The alignment between the APS IRP and the interconnection queue is a very encouraging sign for future growth. Currently, 34% of the operating APS energy mix is renewables or storage. If the next 15 years of development continue to proceed as the IRP lays out, it will add 4,951 MW of renewables and storage capacity and 409 MW of natural gas, resulting in an energy mix that is 64% renewables or storage.

So, what can these trends tell us about the overall future of the APS energy landscape? The data paints an appropriately sunny picture for the state of Arizona. With the amount of development already underway and a strong track record behind them, Arizona Public Service looks poised to maintain its status as one of the leaders of the energy transition.

Want to explore power projects and developer profiles? Learn more about Project Tracking Analytics.

Explore Solution

Picture of Evan Powell

Evan Powell

Evan Powell joined Enverus in 2020 as a research analyst on the Power and Renewables team. His focus areas include tracking power generation, transmission and LMP data within the CAISO region and integrating the Energy Information Administration (EIA) and utility queues data into Enverus PRISM®. He graduated from the Colorado School of Mines with a Bachelor’s degree in Mechanical Engineering and a Master’s in Engineering and Technology Management.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content

data-center-demand
Energy Transition
ByAdam Robinson, Enverus Intelligence® | Research (EIR) Contributor

Hyperscalers' capital expenditure forecasts show a split between expanding and maintaining data center (DC) capacity, with upkeep costs quickly outpacing growth spending.

trading-and-risk
Trading and Risk
ByKiana Cruz

Learn how a European energy giant transformed its trading strategy by breaking free from legacy ETRM systems with Enverus MarketView®. Unlock faster, more profitable energy trades, streamline data management, integrate real-time market insights, and enhance workflows with over 400 trusted...

Enverus Press Release - Alternative fuels M&A focus turns from policy boosts to business resilience
Energy Transition
ByAmyra Mardhani

The clean fuels industry is at a critical juncture. An influx of low-carbon fuels has put downward pressure on U.S. credit prices, reshaping the economic landscape of the sector.

ofs
Business Automation Operators
ByEnverus

Explore key OFS pricing trends for 2025 and learn how you can manage spend and improve efficiency. Stay ahead in the oil and gas industry.

Enverus Press Release - Lessons learned from Eaton and the risk of wildfires spread by transmission lines
Power and Renewables
ByEric Yen

As the energy landscape continues to evolve, grid congestion is becoming increasingly difficult to predict. With rapid additions of new generation and load projects, traders face growing uncertainty and rising risks in the market. The challenge lies in understanding where...

Enverus Press Release - Looking past the CCUS power plant pipe dream
Energy Transition
ByAmyra Mardhani

EIR provides an overview of recent changes and additions to the growing list of Claas VI wells associated with CCS projects in the US.

minerals-management
Minerals
ByPhillip Dunning

Discover 5 crucial tax strategies for mineral and royalty owners to maximize savings and minimize tax liability. Learn about deductions, 1031 exchanges, and more to ensure you don't overpay this tax season.

affordable energy
Energy Transition
ByAdam Robinson, Enverus Intelligence® | Research (EIR) Contributor

DeepSeek’s recently released open-source reasoning, large language model (LLM) V3-R1 has benchmarked closely to OpenAI’s o1 framework.

Enverus Blog
Energy Transition
ByBrynna Foley

As renewable energy development accelerates, interconnection queues have become increasingly congested with an influx of projects looking to connect to the grid.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Register Today

Sign Up

Power Your Insights

Connect with an Expert

Access Product Tour

Speak to an Expert